Plumbing a new bathroom layout starts at the soil pipe: place the toilet first, check waste falls and lengths, then supplies, floor, ventilation and access.
Plan a new bathroom from the drain outwards. Fix the soil pipe position and level, place the toilet within reach of it, then arrange bath, shower and basin so that each waste falls to a connection within its limits. Taps and tiles come afterwards.
Survey
Measure the room, door, window and sloping ceilings. Find the stack, where the branches enter it, joist direction and depth, hot water system and stop valve. Photograph under the bath and any access.
Toilet position
The closer to the stack, the simpler. Approved Document H shows a 100 mm branch for WCs with outlets over 80 mm, with a minimum gradient of about 18 mm per metre for a single connection and, in its branch diagram, a maximum of 6 m for a single WC before further ventilation is considered. Its Table 2 prints 15 m; design to the stricter 6 m. Turning a corner or crossing joists eats height. See moving a toilet.
Other wastes
| Fitting | Trap size in guidance | Layout note |
|---|---|---|
| Basin | 32 mm | Short unventilated runs |
| Bath | 40 mm | Needs floor depth |
| Shower | 40 mm | Tray height may rise |
Longer runs may need a larger pipe or ventilation. Connections into a stack must avoid crossflow between opposite branches, as the guidance illustrates.
For orientation, the same document shows unventilated 40 mm bath branches up to 3 m, or 4 m in 50 mm pipe, falling between 18 and 90 mm per metre. A 32 mm basin branch is limited to about 1.7 m, and the permitted gradient narrows as that length increases.
Floor and structure
A shower moved to a spot over a joist may need a raised tray. A bath moved to mid-span adds load there; the Planning Portal points out strengthening may be needed where use changes. Joists have notch and hole limits.
Supplies
Size pipes for the outlets used together. Gravity systems need short, generous runs. Provide isolating valves and keep cold pipes cool.
Clearances
Draw each fitting with the space needed to use it; see measurements and clearances. A layout that fits on paper may block the door.
Windows, ventilation and power
Showers under windows need waterproof detailing and suitable glazing. Plan a fan and duct to outside under Approved Document F. Electrical positions are restricted around baths and showers.
Approvals
New drainage, structural change and new circuits can fall under building regulations. In England and Wales some changes need notice to the water company before work starts, including a bath over 230 litres. Flats often need consent, and neighbours below care about noise and leaks.
Draw three options
- Minimum change: fittings stay where their wastes are.
- Moderate: swap positions within existing fall.
- Full: new branches and floor work.
Compare each for disruption, access and risk before choosing. The cheapest option is usually the one that leaves the toilet where it is.
Next
Send a plan with the stack marked and photos through the contact form, emailing attachments with your reference. Say which parts of the design are fixed.
Keeping costs predictable
Write down which positions are fixed, which can move and which fittings are already bought. Ask for floor opening, pipe alterations and making good to be listed separately, since concealed conditions can change the work. Agree what happens if joists or old drains are not as expected once the floor is up, and avoid ordering furniture that depends on a pipe position nobody has yet confirmed.
A quick feasibility test
Measure from the stack to the proposed toilet, multiply by the minimum fall and add the pipe diameter and fittings. Compare the total with the depth between joists or boxing height available. If it does not fit on paper, it will not fit on site.
Questions people ask
What should be placed first?
The toilet, because its large pipe and fall limit where it can go.
Can I swap bath and basin positions?
Often, if their wastes can still fall within limits. Check the pipe routes.