Fitting a tray on a solid floor

Published

Fitting a shower tray on a concrete floor: decide where the waste pipe runs, choose legs or a solid bed, prepare and level the slab, then test before tiling.

On a concrete floor the question is where the trap and pipe will go. Either raise the tray so they sit above the slab, or cut a channel and trap recess into the floor. Settle that before choosing the tray, because the answer fixes its height.

Two routes

Route Gains Costs
Raised tray on legs or riser kit No breaking out; pipe reachable behind a panel A step up into the shower
Recessed waste in the slab Low step Dust, damp proofing, reinstatement and little access

Mira's fitting guide describes adjustable trays standing on legs as giving access to the pipes underneath, and gives about 50 mm of fall per metre of waste pipe as typical for its method. Check the figure your own tray and pipe size require.

Measure the fall

Find where the pipe must finish: a gully, stack or existing branch. Measure its height and the horizontal run. Subtract from the height of the trap outlet under each candidate tray. If the outlet is lower than the destination plus the fall, water will not drain by gravity from there.

Before cutting concrete

  • Find underfloor heating, water pipes, cables and gas pipes. Do not cut blind.
  • Check for a damp proof membrane and plan how it will be repaired.
  • In older homes, floor coverings and adhesives may contain asbestos; identify them first.
  • Ask a surveyor or builder before cutting a suspended concrete floor, which may be structural.
  • Upper floor flats often need freeholder consent.

Concrete dust is harmful. Use water suppression or proper extraction and respiratory protection.

Pipes in the floor

Water supply fittings have a specific rule: they must not be embedded in a solid floor. Keep supply pipes out of the slab. For the waste, make a trap that can be cleaned from above and leave a record of the route.

Bedding a solid base tray

The Mira Flight guide calls for a floor that is level, solid, free of movement, dry, clean and suitably primed. Its recommended bed is five parts sand to one of cement at least 10 mm thick, with a suitable construction adhesive as the alternative where that is impractical. Follow the instructions with your own tray, which may differ.

  1. Dry fit tray and waste.
  2. Connect the pipe and test its joints before bedding.
  3. Prime the floor as required.
  4. Spread the bed so the whole base is supported.
  5. Press down and level in every direction.
  6. Keep weight off until it has set.

Concrete is rarely flat

Check with a long level. Fill hollows with a compatible levelling product and let it cure. Do not shim a stone resin tray at the corners over a void.

Test

Pour water in before any wall finish covers the rim. Look at the trap and the first joint, then check that water leaves the whole tray without pooling at an edge. Seal and tile only afterwards.

Reinstating the floor

Where a channel has been cut, pipe joints should be tested before anything covers them. Surround the pipe as the drainage and screed products require, hold it so fresh mortar cannot float or flatten it, and restore the damp proof layer so water from the ground cannot rise through the repair. Allow the new material to dry before bonding a tray or waterproofing over it. Take photographs with a tape in view so a later tiler knows where not to drill, and keep the trap model with them.

Who does what

Breaking out, damp proofing and screed repair may be a builder's work; connecting the waste and tray is the plumbing part. Put the floor height measurements in the contact form and email the tray drawing and a photo of the nearest waste pipe. See waste and trap fitting for the connection itself.